Reports:


Project Report # Type Date Sample Sample Date Version
2024247 -- TCC @ MacArthur... 14277168 Report of In-Place Density Testing Mon, 2020-08-24 14277168 Tue, 2020-08-11 1
2024247 -- TCC @ MacArthur... 14281528 Report of Reinforcing Steel Inspection Wed, 2020-10-14 14281528 Thu, 2020-10-08 1
2024247 -- TCC @ MacArthur... 14284628 Report of In-Place Density Testing Mon, 2020-11-30 14284628 Mon, 2020-11-16 1
2024257 -- St. David's... 18514229 Report of On-Site Activities Wed, 2020-07-01 18514229 Wed, 2020-07-01 1
2024259 -- Skyline Commerce... 14282147 Report of Drilled Pier Inspection Fri, 2020-10-23 14282147 Wed, 2020-10-14 1
2024263 -- 6th &... 18518165 Report of Post Tension Prepour Inspection Wed, 2021-01-20 18518165 Thu, 2021-01-14 1
2024263 -- 6th &... 18518784 Report of On-Site Activities Wed, 2021-03-03 18518784 Fri, 2021-02-26 1
2024263 -- 6th &... 18518812 Report of Post Tension Prepour Inspection Wed, 2021-03-17 18518812 Tue, 2021-03-02 1
2024263 -- 6th &... 18519282 Report of Masonry Inspection Fri, 2021-03-26 18519282 Tue, 2021-03-23 1
2024263 -- 6th &... 18519636 Report of Post Tension Prepour Inspection Fri, 2021-04-09 18519636 Wed, 2021-04-07 1
2024263 -- 6th &... 18519919 Report of Reinforcing Steel Inspection Tue, 2021-04-13 18519919 Mon, 2021-04-12 1
2024263 -- 6th &... 18519987 Report of Reinforcing Steel Inspection Mon, 2021-04-19 18519987 Thu, 2021-04-15 1
2024263 -- 6th &... 18520846 Report of Floor Flatness Survey Mon, 2021-05-24 18520846 Thu, 2021-05-20 1
2024263 -- 6th &... 18522181 Report of Masonry Inspection Tue, 2021-07-20 18522181 Mon, 2021-07-19 1
2024263 -- 6th &... 18522379 Report of Masonry Inspection Tue, 2021-07-27 18522379 Fri, 2021-07-23 1
2024263 -- 6th &... 18522983 Report of Post Tension Inspection Tue, 2021-08-17 18522983 Mon, 2021-08-16 1
2024263 -- 6th &... 18524650 Report of Post Tension Inspection Tue, 2021-10-19 18524650 Thu, 2021-10-14 1
2024263 -- 6th &... 18524886 Report of Reinforcing Steel Inspection Thu, 2021-10-28 18524886 Tue, 2021-10-26 1
2024263 -- 6th &... 18526585 Report of Masonry Inspection Mon, 2021-12-20 18526585 Fri, 2021-12-17 1
2024263 -- 6th &... 18526792 Report of Post Tension Prepour Inspection Tue, 2021-12-28 18526792 Thu, 2021-12-23 1
2024263 -- 6th &... 18527785 Report of Floor Flatness Survey Fri, 2022-02-11 18527785 Mon, 2022-01-24 1
2024263 -- 6th &... 18528279 Report of Floor Flatness Survey Wed, 2022-02-23 18528279 Wed, 2021-10-20 1
2024263 -- 6th &... 18528283 Report of Reinforcing Steel Inspection Tue, 2022-03-01 18528283 Wed, 2022-02-23 1
2024263 -- 6th &... 18528942 Report of On Site Activities Wed, 2022-03-23 18528942 Wed, 2022-03-16 1
2024263 -- 6th &... 18529123 Report of Post Tension Inspection Mon, 2022-03-28 18529123 Mon, 2022-03-21 1